Summer 1994 |
- Purchased Property |
Summer 1995 |
- Put in Septic System |
June 2002 |
- Bought Log Home Kit |
June 2002 |
- Cleared Lot |
July 11, 2002 |
- Secured Building Permit |
July 12, 2002 |
- Initial Excavation |
July 23, 2002 |
- Survey to locate House Pad on Lot |
July 30, 2002 |
- PortaPotty delivered |
August 7, 2002 |
- Footers to be dug (opps problems) |
August 8, 2002 |
- A Solution to solve site problems (we
hope) |
August 10, 2002 |
- More excavation to solve position problem |
August 12, 2002 |
- Begin digging footers |
August 12, 2002 |
- Inspection of footers |
August 13, 2002 |
- Put steel in footers and next inspection |
August 14, 2002 |
- Pour concrete for footers |
August 16, 2002 |
- Blocks Delivered for Foundation |
August 16, 2002 |
- Purchase materials for floor framing |
August 17, 2002 |
- Move materials up the mountain |
August 20, 2002 |
- Foundation Blocks laid |
August 22, 2002 |
- Floor Framing completed |
August 23, 2002 |
- Sub floor complete |
August 23, 2002 |
- Inspection of Temporary Electric Service
(failed) |
August 23, 2002 |
- Fireplace components arrive |
August 23, 2002 |
- Purchased exterior doors and windows |
August 26, 2002 |
- Confirmed Log Delivery for 8-29-2002
|
August 29, 2002 |
- Logs delivered at noon |
August 30, 2002 |
- Day One of log raising with
Dave's help |
August 31, 2002 |
- Day Two and all logs moved
up to site |
September 1, 2002 |
- Day Three 12 courses of logs on 3 walls |
September 2, 2002 |
- Day Four completed main house walls |
September 3, 2002 |
- Day Five Passed Temp Electrical |
September 3, 2002 |
- Gable Ends & Fire Dept burned
debris |
September 4, 2002 |
- Day Six Trusses arrive & installation
begins |
September 5, 2002 |
- Day Seven Trimmed Gables & finished
trusses |
September 6, 2002 |
- Day Eight Installed Roof Decking &
windows |
September 7, 2002 |
- Day Nine Finished decking & rolled
roofing |
September 8, 2002 |
- Day Ten Cleaned Up and headed home |
September 9, 2002 |
- Hired Randy Jenkins to construct porch |
September 30, 2002 |
- Randy finishes porch |
October 5, 2002 |
- Bob and Lyda cleaned the logs |
October 25, 2002 |
- Preserved logs with PeneTreat |
October 26, 2002 |
- Installed outside trim (rough sawn white
pine) |
November 9, 2002 |
- Stained the logs with OrganicClear WR-95 |
March 3, 2003 |
- A quick trip to check on the cabin |
June 12, 2003 |
- Good news! Electric problems solved |
June 14, 2003 |
- Treated Porch with water seal |
June 15, 2003 |
- Built steps, installed screens in rafters |
June 16-17, 2003 |
- Installed sewer line, routed walls for
wiring |
June 18, 2003 |
- Rebuilt the bridge, stained posts |
June 19, 2003 |
- Installed fascia boards and drip cap |
June 20-21, 2003 |
- Framed up interior walls |
August 9, 2003 |
- Purchased plumbing materials |
August 15, 2003 |
- Electricity finally arrives at our
mountain lot |
August 29, 2003 |
- Designed and began construction of a lift |
September 2, 2003 |
- Completed the Charlie Horse, our lift |
September 4, 2003 |
- Completed drain plumbing |
September 5, 2003 |
- Began installing wall paneling |
September 6, 2003 |
- Completed fireplace enclosure |
October 3, 2003 |
- Stained fireplace enclosure |
October 4, 2003 |
- Refurbished spring and installed water
tank |
October 24, 2003 |
- Metal Roof, Soffit & Fascia complete |
October 25, 2003 |
- Completed under house plumbing |
April 25, 2004 |
- Completed plumbing with hot and cold
water |
May 2004 |
-Working on the electrical system |
July 2004 |
-Passed plumbing & electrical inspections |
August 2004 |
-Insulation in interior walls |
September 2004 |
-Finished Interior wood walls |
October 2004 |
-Installed light fixtures in bath &
Winterized |
May 2005 |
-Installed Insulation in Attic and Ceiling |
July 2005 |
-Installed Wood Ceilings and stained
interior |
August 2005 |
-Installed the stonework around the
fireplace |
July 2006 |
-Finished the kitchen |
August 2006 |
-Began installation of hardwood floors |
September 2006 |
-Finished the hardwood floors |
May 2007 |
-Installed Living Room Air conditioner &
heater |
June 2007 |
-Constructed Steps, called for an
inspection |
July 2007 |
-Installed gutters constructed French drain |
July 31, 2007 |
Certificate of Occupancy issued |
|
|
|
|
|
|