| Summer 1994 | - Purchased Property |
| Summer 1995 | - Put in Septic System |
| June 2002 | - Bought Log Home Kit |
| June 2002 | - Cleared Lot |
| July 11, 2002 | - Secured Building Permit |
| July 12, 2002 | - Initial Excavation |
| July 23, 2002 | - Survey to locate House Pad on Lot |
| July 30, 2002 | - PortaPotty delivered |
| August 7, 2002 | - Footers to be dug (opps problems) |
| August 8, 2002 | - A Solution to solve site problems (we hope) |
| August 10, 2002 | - More excavation to solve position problem |
| August 12, 2002 | - Begin digging footers |
| August 12, 2002 | - Inspection of footers |
| August 13, 2002 | - Put steel in footers and next inspection |
| August 14, 2002 | - Pour concrete for footers |
| August 16, 2002 | - Blocks Delivered for Foundation |
| August 16, 2002 | - Purchase materials for floor framing |
| August 17, 2002 | - Move materials up the mountain |
| August 20, 2002 | - Foundation Blocks laid |
| August 22, 2002 | - Floor Framing completed |
| August 23, 2002 | - Sub floor complete |
| August 23, 2002 | - Inspection of Temporary Electric Service (failed) |
| August 23, 2002 | - Fireplace components arrive |
| August 23, 2002 | - Purchased exterior doors and windows |
| August 26, 2002 | - Confirmed Log Delivery for 8-29-2002 |
| August 29, 2002 | - Logs delivered at noon |
| August 30, 2002 | - Day One of log raising with Dave's help |
| August 31, 2002 | - Day Two and all logs moved up to site |
| September 1, 2002 | - Day Three 12 courses of logs on 3 walls |
| September 2, 2002 | - Day Four completed main house walls |
| September 3, 2002 | - Day Five Passed Temp Electrical |
| September 3, 2002 | - Gable Ends & Fire Dept burned debris |
| September 4, 2002 | - Day Six Trusses arrive & installation begins |
| September 5, 2002 | - Day Seven Trimmed Gables & finished trusses |
| September 6, 2002 | - Day Eight Installed Roof Decking & windows |
| September 7, 2002 | - Day Nine Finished decking & rolled roofing |
| September 8, 2002 | - Day Ten Cleaned Up and headed home |
| September 9, 2002 | - Hired Randy Jenkins to construct porch |
| September 30, 2002 | - Randy finishes porch |
| October 5, 2002 | - Bob and Lyda cleaned the logs |
| October 25, 2002 | - Preserved logs with PeneTreat |
| October 26, 2002 | - Installed outside trim (rough sawn white pine) |
| November 9, 2002 | - Stained the logs with OrganicClear WR-95 |
| March 3, 2003 | - A quick trip to check on the cabin |
| June 12, 2003 | - Good news! Electric problems solved |
| June 14, 2003 | - Treated Porch with water seal |
| June 15, 2003 | - Built steps, installed screens in rafters |
| June 16-17, 2003 | - Installed sewer line, routed walls for wiring |
| June 18, 2003 | - Rebuilt the bridge, stained posts |
| June 19, 2003 | - Installed fascia boards and drip cap |
| June 20-21, 2003 | - Framed up interior walls |
| August 9, 2003 | - Purchased plumbing materials |
| August 15, 2003 | - Electricity finally arrives at our mountain lot |
| August 29, 2003 | - Designed and began construction of a lift |
| September 2, 2003 | - Completed the Charlie Horse, our lift |
| September 4, 2003 | - Completed drain plumbing |
| September 5, 2003 | - Began installing wall paneling |
| September 6, 2003 | - Completed fireplace enclosure |
| October 3, 2003 | - Stained fireplace enclosure |
| October 4, 2003 | - Refurbished spring and installed water tank |
| October 24, 2003 | - Metal Roof, Soffit & Fascia complete |
| October 25, 2003 | - Completed under house plumbing |
| April 25, 2004 | - Completed plumbing with hot and cold water |
| May 2004 | -Working on the electrical system |
| July 2004 | -Passed plumbing & electrical inspections |
| August 2004 | -Insulation in interior walls |
| September 2004 | -Finished Interior wood walls |
| October 2004 | -Installed light fixtures in bath & Winterized |
| May 2005 | -Installed Insulation in Attic and Ceiling |
| July 2005 | -Installed Wood Ceilings and stained interior |
| August 2005 | -Installed the stonework around the fireplace |
| July 2006 | -Finished the kitchen |
| August 2006 | -Began installation of hardwood floors |
| September 2006 | -Finished the hardwood floors |
| May 2007 | -Installed Living Room Air conditioner & heater |
| June 2007 | -Constructed Steps, called for an inspection |
| July 2007 | -Installed gutters constructed French drain |
| July 31, 2007 | Certificate of Occupancy issued |